Yocto Project Status 14 February 2023 (WW07)


Stephen Jolley
 

Current Dev Position: YP 4.2 M3

Next Deadline: 20th February 2023 YP 4.2 M3 Build

 

Next Team Meetings:

 

Key Status/Updates:

  • YP 3.1.23 was built and is in QA. There was an intermittent failure during the release build but this was a known issue recurring.
  • Next week is when M3 is due to build and this marks feature freeze for YP 4.2.
  • We saw a number of version upgrades this week (thanks Alex Kanavin).
  • There were also improvements to our runtime testing reliability (thanks Mikko Rapeli).
  • Of the issues discussed in https://lists.openembedded.org/g/openembedded-core/message/176476, the bitbake command timeout and PR serv async io issues still need to be addressed.
  • CVE levels in master are reducing but help in resolving the remaining issues would be appreciated.
  • We have a growing number of bugs in bugzilla, any help with them is appreciated.

 

Ways to contribute:

 

YP 4.2 Milestone Dates:

  • YP 4.2 M3 build date 2023/02/20
  • YP 4.2 M3 Release date 2023/03/03
  • YP 4.2 M4 build date 2023/04/03
  • YP 4.2 M4 Release date 2023/04/28

 

Upcoming dot releases:

  • YP 3.1.23 is built and in QA
  • YP 3.1.23 Release date 2023/02/24
  • YP 4.0.8 build date 2023/02/27
  • YP 4.0.8 Release date 2023/03/10
  • YP 4.1.3 build date 2023/03/06
  • YP 4.1.3 Release date 2023/03/17
  • YP 3.1.24 build date 2023/03/20
  • YP 3.1.24 Release date 2023/03/31
  • YP 4.0.9 build date 2023/04/10
  • YP 4.0.9 Release date 2023/04/21
  • YP 4.1.4 build date 2023/05/01
  • YP 4.1.4 Release date 2023/05/13
  • YP 3.1.25 build date 2023/05/08
  • YP 3.1.25 Release date 2023/05/19
  • YP 4.0.10 build date 2023/05/15
  • YP 4.0.10 Release date 2023/05/26

 

Tracking Metrics:

 

The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:

https://wiki.yoctoproject.org/wiki/TSC

 

The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status

 

[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]

 

Thanks,

 

Stephen K. Jolley

Yocto Project Program Manager

(    Cell:                (208) 244-4460

* Email:              sjolley.yp.pm@...