Attending: Paul, Davest, Dirk, Richard, Saul, Alex, Mark,
Jessica, Bruce, Darren
Goal: Review the release criteria and make a clear decision
to see that we're ready to release.
Summary: Launch criteria met with these exceptions:
*
BSPs for Tunnel Creek coming by end of November
*
Documentation and web site will become live over the weekend for check out
*
One high open bug (issue with zypper on targets) to be addressed early in post-launch
time frame, OK for now
*
Medium open bug count is higher than desired; major focused effort on resolving
bugs in next dev cycle
*
Full test report for all architectures pending - will review by end of week
Decision: Go for launch
Details:
Features Completeness - 100%
Exceptions
relative to the features on the product requirement:
Tunnel
Creek BSP - will be available by end of November
Documentation
- the basic pieces are there, more are coming in post 0.9 launch
Several
engineers unfamiliar with the project are taking the existing bits and making
sure they can do a build without hand-holding. This should be complete by
latest on Sunday.
Bug Status:
Note:
these bug count goals are suggestions for now, we need to
* No High Bugs. Actual bugs below:
190
- an enhancement, will be addressed for the 0.9 release
443
- zypper segfaulting on some architectures parsing package list on some images.
Zypper really needs to be rearchitected early in the 1.0 cycle. Just use RPM
directly. Document.
477
- Certain Python modules don't work on the target, late breaking, will
downgrade to medium
* Medium Bugs < 15
51
total are open now, 7 will be addressed before launch
Does
not meet the criteria, but as these are documented we believe they are acceptable
to ship with.
We
need to do a serious effort to reduce the bug count for 1.0.
We
also need to analyze our bug handling process in the next planning meeting.
* Low Bugs < 30
37
are open now.
* No Undecided Bugs
May
include some which come in very late and have not been dispositioned yet.
Unit Tests Completed - 100%
Test Cases Completed - 100%
What
was planned was completed. Would like to expand this going forward.
Sanity Test – 100%
BAT Testing – 100%
Full Test – 90% Passing
93%
completion for all architectures for QEMU and iA hardware
Need
report on ARM, PPC and MIPs hardware - Saul
Legal & License – Have Legal & Open Source PDT
Approval
Have
completed all required legal review
Docs – Pass stakeholder review & Publish to
Website
Currently
in process and under review, should be available for review